Dependencies and gates
The start gate, the finish gate, cycles, and what cancelling or archiving a task does to its dependents.
Start gate
A task's start gate is satisfied when every reference in depends_on resolves to a live task
whose status is DONE. Otherwise the reference is unsatisfied with exactly one reason:
| Reason | Condition |
|---|---|
not-done | The task exists, is live and open. |
cancelled | The task exists and is CANCELLED. |
missing | No task at that path in the target tree, live or archived. |
archived | The path exists only under the target tree's .archive/. |
malformed | The task exists but its manifest cannot be parsed (see Structure). |
unresolved-project | An external reference whose path does not resolve to a tree. |
not-checked-out | An external reference through a configured alias whose directory is absent. |
unsupported-version | An external reference into a tree whose version this implementation does not support, a v1 tree included. |
A reference that fails to parse MUST resolve as unsatisfied and MUST NOT abort the query;
reporting it as missing is RECOMMENDED. A task with an empty depends_on satisfies the start
gate trivially.
The start gate MUST be checked by claim and by done; an explicit force MAY override it.
Non-normative
Cancelled work never satisfies a dependency: nothing can be built on it. It does satisfy a finish gate: the parent's deliverable was redefined, explicitly.
A dependency on a cancelled task is therefore not blocked but stranded: waiting cannot open
the gate. Only a person can, in one of three ways — cancel the dependent too, because its premise
died with the dependency; remove the reference, because the dependent can proceed without it; or
point the reference at whatever now does that work. A dependency is a monitor, not a link: the
tool never cancels dependents on its own, because any of the three may be right and the tool
cannot tell which. It makes the stranding visible instead — in the result of the cancel that
caused it, in every overview as blocked by A (cancelled), and in validation — and a reopen of
the dependency unblocks the dependents by itself, because blocking is computed.
Finish gate
A task's finish gate is satisfied when:
- every live child is resolved (
DONEorCANCELLED), and - every reference in
finishes_afterresolves to a live task that is resolved.
An unresolvable finishes_after reference blocks, with the reasons of the table above. The
finish gate MUST be checked by done. cancel does not check it: it cascades to the children
instead and ignores finishes_after (see Containment).
Consequences an implementation MUST enforce:
- A task MUST NOT be created, moved or restored under a resolved parent.
- A child of a resolved parent MUST NOT be reopened while the parent is resolved.
- A resolved task with a live open descendant is a validation error.
Non-normative
The finish gate is a constraint, not a derivation. The parent's status stays
a manual fact; the tool refuses done while children are open, and reports the parent as
closable when they are not. Nothing is written on the parent's behalf: finishing an epic forces
one explicit decision per child, while cancelling it is one decision for the whole subtree.
Cycles
Gate references form one graph with two kinds of edges: a depends_on reference (the target must
be done before this task starts) and a finish edge from each child, and from each
finishes_after reference, to the task (the source must be resolved before this task is done).
A cycle in that graph means the tasks in it can never all resolve.
- An implementation MUST detect cycles among local references during validation and report them as errors.
- An implementation that offers dependency editing MUST refuse a self-reference, a reference to a task that does not exist, a reference from a task to its own ancestor (a guaranteed deadlock with the finish edge), and any reference that would introduce a local cycle; it MUST authorize the edit as it authorizes a transition of the task (Authorization).
- Cross-tree edges MUST NOT be assumed traversable. An implementation SHOULD include them in cycle
detection when the trees are reachable through
projects:, and MUST otherwise treat them as non-edges.
Cancellation and deletion interaction
Cancelling a task that other open tasks depend on strands them (see the note under
Start gate). cancel MUST NOT refuse for that reason — cancellation is a decision
about the cancelled task — but its result MUST list, as dependents, every open task whose
depends_on names a task the command cancelled, in the local tree and in the trees reachable
through projects:, so that the decision about them is taken while the decider is present. A
cascade lists the dependents of every task it reached.
Archiving a task that open tasks reference leaves those tasks permanently blocked. An
implementation MUST refuse such an archive by default, MUST name the dependents, and MAY offer an
explicit override, reporting which tasks were left blocked. A resolved task's reference to an
archived task concerns nobody until that task is reopened; validation reports it then. Because archived paths remain
reserved, recreating a task at the same path MUST fail rather than silently reconnect those
references; a purge of the entry (see .archive/) is the explicit decision to allow
it.